In an MRP system, component demand is:

In an MRP system, component demand is: Correct Answer calculated by the MRP system from the master production schedule

MRP stands for material requirement planning. It is a computer based system that takes master production schedule (MPS) to explode it into required amount of raw materials, parts, sub-assemblies, and assemblies needed in each of the planning horizon, and then reducing these material requirements to account for materials that are in inventory or on order and finally developing a schedule of order for purchased materials and produced parts over the planning horizon