Gantt charts indicate

Gantt charts indicate Correct Answer Comparison of actual progress with the scheduled progress

Gantt charts are mainly used to allocate resources to activities. The resources allocated to activities include staff, hardware, and software. Gantt charts are useful for resource planning. A Gantt chart is a special type of bar chart where each bar represents an activity. The bars are drawn along a timeline. The length of each bar is proportional to the duration of time planned for the corresponding activity.