In PERT chart, the activity time distribution is

In PERT chart, the activity time distribution is Correct Answer Beta

Explanation:

CPM does not directly model uncertainty.

PERT was developed to address the needs of projects which are being done for the first time – a challenge to estimate activity duration.

PERT (Program Evaluation and Review Technique) uses 3 cases:

  • Most Optimistic
  • Most Pessimistic
  • Most likely durations

 

PERT determines the probability for each duration, whereas CPM considers the most likely duration.

In the standard PERT analysis, the distribution assumed for the activity times is a Beta distribution.

[ alt="F1 S.S. N.J 19.07.19 D 8" src="//storage.googleapis.com/tb-img/production/19/07/F1_S.S._N.J_19.07.19_D%208.PNG" style="width: 460px; height: 340px;">

[ alt="F1 S.S. N.J 19.07.19 D 9" src="//storage.googleapis.com/tb-img/production/19/07/F1_S.S._N.J_19.07.19_D%209.PNG" style="width: 457px; height: 329px;">

Related Questions

In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression
Activity slack or float of any event on a PERT/CPM chart is represented by
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________