Consider the following statements in respect of PERT and CPM: 1. PERT is event-oriented while CPM is activity-oriented. 2. PERT is probabilistic while CPM is deterministic. 3. Levelling and smoothing are the techniques related to resource scheduling in CPM. Which of the statements given above are correct?

Consider the following statements in respect of PERT and CPM: 1. PERT is event-oriented while CPM is activity-oriented. 2. PERT is probabilistic while CPM is deterministic. 3. Levelling and smoothing are the techniques related to resource scheduling in CPM. Which of the statements given above are correct? Correct Answer 1, 2 and 3

Explanation:

A project may be defined as a combination of interrelated activities which must be executed in a certain order before the entire task can be completed.

The aim of planning is to develop a sequence of activities of the project so that the project completion time and cost are properly balanced.

To meet the objective of systematic planning, the management has evolved several techniques applying network strategy.

PERT (Programme Evaluation and Review Technique) and CPM (Critical Path Method) are network techniques which have been widely used for planning, scheduling and controlling the large and complex projects.

  • PERT (Project Evaluation and Review Technique) approach takes account of the uncertainties. In this approach, 3-time values are associated which each activity. So it is probabilistic.

[ src="https://storage.googleapis.com/tb-img/production/17/01/CIL_ME_Subject%20test%2010_Images-11.PNG">

  • CPM (Critical Path Method) involves the critical path which is the largest path in the network from starting to ending event and defines the minimum time required to complete the project. So it is deterministic.

Difference between PERT and CPM (Critical Path Method)

PERT

CPM

1. Probabilistic approach

1. Deterministic approach

2. Three-time estimate

2. One - time estimate

3. Event oriented network model

3. Activity-oriented network model

4. The slack concept is used

4. Float concept is used

5. Project crashing is not possible

5. Project crashing is possible

6. Deals with probabilistic time estimates

6. Deals with deterministic time estimates

Related Questions

The following are the conditions for selecting list of a suitable candidates to be called for interview after the written test for the recruitment is conducted/ organized for management-level persons of a multi-national company. For providing accounting services and sales the candidates must (a) be holding a graduation in basic science with 65% or above or B. E degree with 55% and above marks (b) have passed the written test with 70% or above marks (c) the age must be in the group 25 to 30 years as on 1/4/18 (d) have experience in an accounting firms for three years and diploma in accounting with 60% or above marks (e) be presently drawing CTC of 6 Lakhs per annum and above In case the applicant who satisfies all other terms above except 1) at (a) above, then be referred as Junior Accountant 2) at (d) & (e) above then be referred as Trainee-Accountant Satisfying all the above with experience of 5 years then be referred as senior-Accountant Satisfying all the above criteria (a-e) with CA/ ICWA / MBA (Finance) then be refereed as manager (Accounts) Read all the above information and answer the following question Shravani has passed H. SC with 72% of marks. She has done diploma in accountancy with 62% of marks. She was working with an organization in the field of accounting in the field of accounting from 4 years and was drawing CTC of 6.5 Lakhs presently. She is 28yrs as on July 2018. She may referred for the position of: