The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect.
Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities.
Statement II The activities in a critical path can be preponed or postponed.
The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect.
Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities.
Statement II The activities in a critical path can be preponed or postponed. Correct Answer Both statements are incorrect