The basic difference between PERT and CPM is that

A PERT deals with events and CPM with activities
B Critical path is determined in PERT only
C Costs are considered on CPM only and not in PERT
D Guessed times are used in PERT and evaluated times in CPM

Correct Answer: Guessed times are used in PERT and evaluated times in CPM

CPM which is a method to control costs and time. PERT deals with unpredictable activities, but CPM deals with predictable activities.
PERT is used where the nature of the job is non-repetitive.
In contrast to, CPM involves the job of repetitive nature.