Critical path on PERT/CPM chart is obtained by joining the events having

Critical path on PERT/CPM chart is obtained by joining the events having Correct Answer Minimum slack

Slack time can be defined as the amount of time an task can be delayed without causing another task to be delayed or impacting the completion date of your project.
Critical path on PERT/CPM chart is obtained by joining the events having Minimum slack

Related Questions

The letters P, Q, R, S, T and U are to be placed one per vertex on a regular convex hexagon, but not necessarily in the same order. Consider the following statements: The line segment joining R and S is longer than the line segment joining P and Q. The line segment joining R and S is perpendicular to the line segment joining P and Q. The line segment joining R and U is parallel to the line segment joining T and Q. Based on the above statements, which one of the following options is CORRECT?