In a PERT chart A All activities should be numbered B Only important activities should be numbered C Only critical activities are numbered D Only selected activities are numbered In a PERT chart Correct Answer All activities should be numbered In a PERT chart All activities should be numbered Bissoy MCQ Team Mechanical Engineering Industrial Engineering And Production Management