The cantilever method has been successfully used in the span range of ____________
The cantilever method has been successfully used in the span range of ____________ Correct Answer 50-200
The cantilever method has been successfully used in the span range of 50-200m and for small spans of less than 50m and for elevated roads or flyovers were scaffolding beneath the structure must be avoided precast segmental construction is preferred and at present for spans over 70m, prestressed concrete single or multi cell box girders complete successfully with steel construction.