The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____
The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____ Correct Answer 3 cum
Sand = 4 cum Ordinary soil = 3 cum Compacted soil = 2 cum Rock = 1 cum.