Determine the pondage factor if the plant is working at peak time of 16 hrs?
Determine the pondage factor if the plant is working at peak time of 16 hrs? Correct Answer 1.5
Pondage factor = T1/T2 = (Total number of hours in one day)/(Total number of hours plant is running) P.F = 24/16 = 1.5.