After 100 days, remaining work = (1-2.515)=(1-16)=6-16=56 part of work Remaining days = 300-100=200 days Now, 16 part of work is done in 100 days by 45 men ∴56 part of work is done in 200 days by =45×100×6×5200×6=112.5=113 men ∴Number of extra men needed = 113-45 = 68 (ans.)
You need to log in to continue.
You need to download the app to make a call.