1 Answers
LCM of 2 and 3 is 6
Work done in first 6 days =
Remaining work =
Next 3 days work done by them=
Remaining work after 9 days =
In 10th days, B will help A, thus work done by them after 9 days=
Remaining work=
In 11th days, A alone can do part of work which is the amount of remaining work.
Total 11 days will be required to complete the whole work. ans.
8 views
Answered