Rahim can do in 80 days = 1 work

Rahim can do in 1 days = 180part of work

Rahim can do in 10 days=1080=180 part of work

Remaining work= 1-18=78 part of work

Again, Karim can do 78 part in 42 days.

Karim can do 1 part= 42×87=48 days

Karim can do in 1 day = 148 part of work

(Rahim + Karim) can do in 1 day = 180+148=3+5240=130

So, Rahim + Karim can do the work in 30 days, ans.