Materials Requirements Planning (MRP):

  • Materials requirements planning is a simple system of calculating arithmetically the requirements of the input materials at different points of time based on the actual production plan.
  • It can be seen from the figure that an MRP system has three major input components:

The inputs to the MRP system are :

  1. Master production schedule
  2. Inventory status file
  3. Bill of materials (BOM)

[ alt="RRB JE ME 40 14Q IM Part 3 Hindi - Final Diagrams Deepak images Q8" src="https://storage.googleapis.com/tb-img/production/19/06/RRB_JE_ME_40_14Q_IM_Part_3_Hindi%20-%20Final_Diagrams_Deepak_images_Q8.PNG">

Master Production Schedule (MPS): 

  • MPS is designed to meet the market demand (both the firm orders and forecasted demand) in the future in the taken planning horizon.
  • MPS mainly depicts the detailed delivery schedule of the end products. However, orders for replacement components can also be included in it to make it more comprehensive.

Bill of Materials (BOM) File: 

  • BOM represents the product structure.
  • It encompasses information about all sub-components needed, their quantity, and their sequence of build-up in the end product. 
  • Information about the work centers performing build-up operations is also included in it.

[ alt="RRB JE ME 40 14Q IM Part 3 Hindi - Final Diagrams Deepak images Q8a" src="https://storage.googleapis.com/tb-img/production/19/06/RRB_JE_ME_40_14Q_IM_Part_3_Hindi%20-%20Final_Diagrams_Deepak_images_Q8a.PNG" style="width: 615px; height: 371px;">

Inventory Status File: 

  • The inventory status file keeps an up-to-date record of each item in the inventory.
  • Information such as item identification number, quantity on hand, safety stock level, quantity already allocated, and the procurement lead time of each item is recorded in this file.