1. Rs. 258.2 and Rs. 338.8
  2. Rs. 348.2 and Rs. 248.8
  3. Rs. 230.2 and Rs. 366.8
  4. Rs. 358.2 and Rs. 238.8
4 views

1 Answers

Option 4 : Rs. 358.2 and Rs. 238.8

A and B can complete a piece of work in 24 and 36 days respectively,

Let total work be 72 units,

⇒ One day work of A = 3 units

⇒ One day work of B = 2 units

⇒ A’s share = 3/5 × 597 = Rs. 358.2

⇒ B’s share = 2/5 × 597 = Rs. 238.8