1 Answers
Option 1 : 24
A can do a piece of work in 20 days
Part of work A can do in a day = 1/20
B can do a piece of work in 30 days.
Part of work B can do in a day = 1/30
∴ Part of work A and B can do in 5 days together = 5/20 + 5/30 = 25/60 = 5/12
∴ Remaining part of work
= 1 - (5/12)
= 7/12
C finishes 7/12th part of the work in 14 days
∴ C can complete the whole work alone in 14/(7/12) = 24 days