1 Answers

Option 2 : 48

Let A’s 1 day work = x

B’s 1 day work = y

Then, x+ y = 1/16 and 8x + 32y = 1

Solving these two equations, we get

x = 1/24 and y = 1/48

So, B will complete work in 48 days