Option 4 : 60 days
Given:
A and B can complete the work in = 15 days
B and C can complete the work in = 12 days
C alone can complete the work in = 30 days
Formula:
Total work = Efficiency × Time
Calculation:
Total work = 60 unit (LCM of 15, 12 and 30)
Efficiency of A and B = 60/15 = 4 units/day
Efficiency of B and C = 60/12 = 5 units/day
Efficiency of C = 60/30 = 2 units/day
Now,
Efficiency of B = 5 – 2 = 3 units/day
Efficiency of A = 4 – 3 = 1 unit/day
∴ Time taken by A to complete the whole work = 60/1 = 60 days