1 Answers
Option 2 : 102 days
Efficiency ratio of A, B and C = 7 : 5 : 8
Total work = 42 × (7 + 5 + 8) = 840
Work done by B and C in 21 days = (5 + 8) × 21 = 273
Remaining work = 840 – 273 = 567
Remaining work A will complete in = 567/7 = 81 days
Total time = 21 + 81 = 102 days
7 views
Answered