Sachin is 2 times faster than Shivam. Shivam can finish a work alone in 36 days. If Sachin and Shivam started working together and Sachin left the work 3 days before the completion of work. How much time will it take to complete the work?
Sachin is 2 times faster than Shivam. Shivam can finish a work alone in 36 days. If Sachin and Shivam started working together and Sachin left the work 3 days before the completion of work. How much time will it take to complete the work? Correct Answer 14 days
Calculation:
∵ Efficiency is always inversely proportional to time.
|
|
Sachin : Shivam |
|
Efficiency |
2 : 1 |
|
Time |
1 : 2 |
Time taken by Shivam = 2 units = 36 days
Time taken by Sachin = 1 unit = 18 days
Let Total work = L.C.M of 18 and 36 = 36 units
Efficiency of Shivam = 1 unit/day
Efficiency of Sachin = 2 units/day
Total work done by Sachin in 3 days = 2 × 3 = 6 units
Now New Total work = 36 + 6 = 42 units
∴ Total time taken to complete the work = 42/3 = 14 days