With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the work is finished in 53/3 days. How many days will each take individually to execute the work?
With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the work is finished in 53/3 days. How many days will each take individually to execute the work? Correct Answer P = 35/3 days; Q = 35 days
Let P's 1 day work = P and Q's 1 day work = Q
If P start the work, working on alternate days, P and Q can finish a work in 17 days.
P works for = 9 days
Q works for = 8 days
Total work = 9P + 8Q
If Q works on the first day and P and Q work alternately, the work is finished in 53/3 days
53/3 = 17 + 2/3 Days
Q works for = 9 days
P work for = 8 + (2/3) = 26/3 days
Total work = 9Q + 26P/3
According to the question
9P + 8Q = 9Q + 26P/3
⇒ 9P – 26P/3 = 9Q – 8Q
⇒ P/3 = Q
⇒ P : Q = 3 : 1
Total work = 9P + 8Q = 9 × 3 + 8 × 1 = 35
Q alone can finish the whole work in = 35/1 = 35
P alone can finish the whole work in = 35/3 days