12 labourers working 4 hours a day can finish a work in 15 days. If the labourers work 8 hours a day, then how many labourers are required to finish the same piece of work in 9 days?
12 labourers working 4 hours a day can finish a work in 15 days. If the labourers work 8 hours a day, then how many labourers are required to finish the same piece of work in 9 days? Correct Answer 10
Let, 1 labourer do 1 unit work per day.
Then, total work = 12 × 4 × 15 = 720 units
Now, total hours = 8
Total days = 9
Numbers of labourers required = N
Then,
N × 8 × 9 = 720
⇒ N = 10
Hence, option 1) is correct.