A cleaning company employs 42 sweepers to clean a building in 25 days. 10 days later, 12 sweepers left the job. If the cleaning work is to be finished in 10 days, how many more cleaning workers need to be hired? A. 30 B. 32 C. 33 D. 21
A cleaning company employs 42 sweepers to clean a building in 25 days. 10 days later, 12 sweepers left the job. If the cleaning work is to be finished in 10 days, how many more cleaning workers need to be hired? A. 30 B. 32 C. 33 D. 21 Correct Answer C
Given:
The initial number of sweepers is 42
The initial number of days is 25
After 10 days 12 sweepers left.
The remaining work has to be finished in 10 days.
Concept used:
Here, we can use the unitary method
Formula used:
W1/W2 = (M1D1)/(M2D2)
Where W1 is initial work, W2 is remaining work,
M1 is the initial number of men, M2 is the final number of men
D1 is the initial number of days, D2 final number of days
Calculation:
42 sweepers in 25 days can complete 1 unit of work
42 sweeper in 10 days can complete = (10/25) unit of work = 2/5 unit of work
So, the remaining work is = (1 - 2/5) = 3/5 unit of work
So, the remaining sweepers = (42 - 12) = 30
Now, according to the question, M1 = 42, D1 = 10, D2 = 10
Let the required number of sweepers be X
So, the total number of sweeper M2 = (30 + X)
Now, we can say
(2/5)/(3/5) = (42 × 10)/{(30 + X) × 10}
⇒ 2/3 = 42/(30 + X)
⇒ 30 + X = 63
⇒ X = 33
∴ 33 more cleaning workers need to be hired.