Rohit completes 30% of work in 7.5 days. Raju is 50% as efficient as Rohit, Venu is 50% as efficient as Raju. Now Raju and Venu joined with Rohit for the rest of the work then in how many days will take to complete the remaining work.
Rohit completes 30% of work in 7.5 days. Raju is 50% as efficient as Rohit, Venu is 50% as efficient as Raju. Now Raju and Venu joined with Rohit for the rest of the work then in how many days will take to complete the remaining work. Correct Answer 10 days
Given
Rohit completes 30% of work in 7.5 days.
Raju is 50% as efficient as Rohit
Venu is 50% as efficient as Raju
Formula used
Work = Time × Efficiency
Calculation
Rohit takes 25 days to complete the work
Raju takes 50 days
Venu takes 100 days
Now 70% work is left
Part of the work they can complete in 1 day = (1/25 + 1/50 + 1/100) = 7/100
Hence, the remaining work (70% of total work) is completed in = (70/100) × (100/7) = 10 days
∴ The remaining work is completed in 10 days.
মোঃ আরিফুল ইসলাম
Feb 20, 2025