Rohit completes 30% of work in 7.5 days. Raju is 50% as efficient as Rohit, Venu is 50% as efficient as Raju. Now Raju and Venu joined with Rohit for the rest of the work then in how many days will take to complete the remaining work.

Rohit completes 30% of work in 7.5 days. Raju is 50% as efficient as Rohit, Venu is 50% as efficient as Raju. Now Raju and Venu joined with Rohit for the rest of the work then in how many days will take to complete the remaining work. Correct Answer 10 days 

Given  

Rohit completes 30% of work in 7.5 days.

Raju is 50% as efficient as Rohit

Venu is 50% as efficient as Raju

Formula used 

Work = Time × Efficiency

Calculation

Rohit takes 25 days to complete the work

Raju takes 50 days

Venu takes 100 days

Now 70% work is left

Part of the work they can complete in 1 day = (1/25 + 1/50  + 1/100) = 7/100 

Hence, the remaining work (70% of total work) is completed in = (70/100) × (100/7) = 10 days

∴ The remaining work is completed in 10 days.

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.