Sunil, Deepak and Dinesh together can complete a work in 70 days. Sunil and Dinesh together can complete the same work in 120 days. In how many days Deepak alone can complete the same work?
Sunil, Deepak and Dinesh together can complete a work in 70 days. Sunil and Dinesh together can complete the same work in 120 days. In how many days Deepak alone can complete the same work? Correct Answer 168
Given:
Sunil, Deepak and Dinesh together can complete a work in 70 days.
Sunil and Dinesh together can complete the same work in 120 days
Calculation:
Let Deepak alone can complete the same work in ‘y’ days
Work done by Deepak in 1 day = 1/y units
Sunil and Dinesh together can complete the same work in 120 days
Work done by Sunil and Dinesh in 1 day = 1/120 units
Sunil, Deepak and Dinesh together can complete a work in 70 days
Work done by Sunil, Deepak and Dinesh in 1 day = 1/70
⇒ 1/120 + 1/y = 1/70
⇒ 70 × (y + 120) = 120y
⇒ 50y = 8400
⇒ y = 168 days
∴ Deepak alone can complete the same work in 168 days.