Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work? Correct Answer 84 days
Given:
Anil, Deepak and Dinesh together can complete a work in 35 days.
Anil and Dinesh together can complete the same work in 60 days
Calculation:
Let Deepak alone can complete the same work in ‘y’ days
Work done by Deepak in 1 day = 1/y units
Anil and Dinesh together can complete the same work in 60 days
Work done by Anil and Dinesh in 1 day = 1/60 units
⇒ 1/60 + 1/y = 1/35
⇒ 35 × (y + 60) = 60y
⇒ 25y = 2100
⇒ y = 84 days
∴ Deepak alone can complete the same work in 84 days.
মোঃ আরিফুল ইসলাম
Feb 20, 2025