30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task? A. 12 days B. 10 days C. 15 days D. 18 days E. 20 days
30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task? A. 12 days B. 10 days C. 15 days D. 18 days E. 20 days Correct Answer B
Let, work will be completed in x days
According to the question,
⇒ 30 × 5 × 16 = 40 × 6 × x
⇒ 240x = 2400
⇒ x = 10
∴ Work will be completed in = 10 days