As shown in the following table, a project consists of seven activities. Find out project duration: Activity Time required (in weeks) Immediate Predecessor P 7 - Q 4 - R 2 Q S 11 P T 9 P, R U 9 Q V 4 T, U

As shown in the following table, a project consists of seven activities. Find out project duration: Activity Time required (in weeks) Immediate Predecessor P 7 - Q 4 - R 2 Q S 11 P T 9 P, R U 9 Q V 4 T, U Correct Answer 20 weeks

Explanation:

[ alt="F1 Killi 17-3-22 Savita D1" src="//storage.googleapis.com/tb-img/production/22/03/F1_Killi_17-3-22_Savita_D1.png" style=" width: 352px; height: 301px;">

The Critical Path is P - Y - V

The Duration of the Project is 20 Weeks

TE - Schedule Start Time (Earliest)

TL - Scheduled Latest Finish Time

Related Questions

Statement (I): Crashing of project duration always increases the cost of the project on its completion, no matter what the indirect, or overhead, costs are. Statement (II): The critical path along the project activities network diagram is compressed in the process of investigating the crashing of the project duration, and not the non-critical activities, up to a certain stage of crashing.