As shown in the following table, a project consists of seven activities. Find out project duration: Activity Time required (in weeks) Immediate Predecessor P 7 - Q 4 - R 2 Q S 11 P T 9 P, R U 9 Q V 4 T, U
As shown in the following table, a project consists of seven activities. Find out project duration: Activity Time required (in weeks) Immediate Predecessor P 7 - Q 4 - R 2 Q S 11 P T 9 P, R U 9 Q V 4 T, U Correct Answer 20 weeks
Explanation:
[ alt="F1 Killi 17-3-22 Savita D1" src="//storage.googleapis.com/tb-img/production/22/03/F1_Killi_17-3-22_Savita_D1.png" style=" width: 352px; height: 301px;">
The Critical Path is P - Y - V
The Duration of the Project is 20 Weeks
TE - Schedule Start Time (Earliest)
TL - Scheduled Latest Finish Time