Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project Activity Duration (days) 1-2 2 2-3 1 4-3 3 1-4 3 2-5 3 3-5 2 4-5 4 The critical path (CP) in the network is

Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project Activity Duration (days) 1-2 2 2-3 1 4-3 3 1-4 3 2-5 3 3-5 2 4-5 4 The critical path (CP) in the network is Correct Answer 1-4-3-5

Concept:

Trick: Whenever activity is mentioned take points on node itself to avoid the confusion.

[ alt="F1 S.C 13.12.19 Pallavi D 3" src="//storage.googleapis.com/tb-img/production/19/12/F1_S.C_13.12.19_Pallavi_D%203.png" style="width: 305px; height: 137px;">

And take the duration on path.

→ Note: Find the durations of path given in option and then take the path with max duration

Because, Critical path is the minimum time required to completed the task or path with maximum duration

1) 1 – 2 – 3 – 5 = 5 days

2) 1 – 2 – 3 – 4 – 5 (No path is formed) ∵ 3 – 4 path is not a path

3) 1 – 4 – 3 – 5 = 8 days

4) 1 – 4 – 5 → 7 days

Hence from the above calculation we can see that path in the option(c) is the critical path.

Related Questions

Statement (I): Crashing of project duration always increases the cost of the project on its completion, no matter what the indirect, or overhead, costs are. Statement (II): The critical path along the project activities network diagram is compressed in the process of investigating the crashing of the project duration, and not the non-critical activities, up to a certain stage of crashing.