Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project Activity Duration (days) 1-2 2 2-3 1 4-3 3 1-4 3 2-5 3 3-5 2 4-5 4 The critical path (CP) in the network is
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project Activity Duration (days) 1-2 2 2-3 1 4-3 3 1-4 3 2-5 3 3-5 2 4-5 4 The critical path (CP) in the network is Correct Answer 1-4-3-5
Concept:
Trick: Whenever activity is mentioned take points on node itself to avoid the confusion.
[ alt="F1 S.C 13.12.19 Pallavi D 3" src="//storage.googleapis.com/tb-img/production/19/12/F1_S.C_13.12.19_Pallavi_D%203.png" style="width: 305px; height: 137px;">
And take the duration on path.
→ Note: Find the durations of path given in option and then take the path with max duration
Because, Critical path is the minimum time required to completed the task or path with maximum duration
1) 1 – 2 – 3 – 5 = 5 days
2) 1 – 2 – 3 – 4 – 5 (No path is formed) ∵ 3 – 4 path is not a path
3) 1 – 4 – 3 – 5 = 8 days
4) 1 – 4 – 5 → 7 days
Hence from the above calculation we can see that path in the option(c) is the critical path.