Statement (I): A merging node will have a uniquely determinable Late Event Time. Statement (II): A merging node is defined as a node where more than one incoming activity arrow leads in
Statement (I): A merging node will have a uniquely determinable Late Event Time. Statement (II): A merging node is defined as a node where more than one incoming activity arrow leads in Correct Answer Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
Concept:
Merging Node: When more than one activity comes and joins a node such a node is known as the merging node.
A merging node will have a uniquely determinable Late Event Time.
Bursting Node: When more than one activity leaves a node such a node is known as bursting node.
Merging and Burst event: An activity may be a merge and burst event at the same time as with respect to some activities it can be a merge event and with respect to some other activities it may be a burst event.
[ alt="F1 A.M Madhu 10.07.20 D11" src="//storage.googleapis.com/tb-img/production/20/07/F1_A.M_Madhu_10.07.20_D11.png" style="width: 360px; height: 112px;">
Earliest start (ES): this is the earliest possible time that an activity can begin. All immediate predecessors must be finished before an activity can start.
Latest start (LS): this is the latest time that an activity can begin and not delay the completion time of the overall project. If the earliest start and latest start times are the same then the activity is critical.
Earliest finish (EF): this is the earliest possible time that an activity can be finished (= earliest start time + activity completion time).
Latest finish (LF): this is the latest time that an activity can be finished and not delay the completion time of the overall project ( = latest start time + activity completion time). As with start times, the activity is critical if the earliest finish and latest finish times are the same.
Slack: this is the difference between the earliest start time and the latest start time (which in turn is equal to the difference between the latest start time and the latest finish time), i.e. Slack = LS - ES = LF - EF
Hence, both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I).