There are two person A and B.A alone can complete the whole work in x days and B alone can complete the whole work in y days. Working together they can complete the whole work in 12 day. Which of the following statements is/are true regarding x and y? A) 20 days and 30 days B) 25 days and 300/13 days C) 32 days and 96/5 days D) 40 days and 10 days
There are two person A and B.A alone can complete the whole work in x days and B alone can complete the whole work in y days. Working together they can complete the whole work in 12 day. Which of the following statements is/are true regarding x and y? A) 20 days and 30 days B) 25 days and 300/13 days C) 32 days and 96/5 days D) 40 days and 10 days Correct Answer A, B and C
From statement A
⇒ (1/20) + (1/30) = (1/12)
⇒ (2 + 3)/60 = 1/12
⇒ 1/12 = 1/12 (Satisfied)
From statement B
⇒ (1/25) + (13/300) = 1/12
⇒ (12 + 13)/300 = 1/12
⇒ 1/12 = 1/12 (Satisfied)
From statement C
⇒ (1/32) + (5/96) = 1/12
⇒ 1/12 = 1/12 (Satisfied)
Hence option 3 is correct.