A company employs 15 persons working 44 hours a week . If 4 persons are ill, how many hours a week would the rest have to work to make up the time lost ?
A
60
B
55
C
50
D
None of these
Correct Answer: 60
Remaining people = 15 - 4 = 11 15 people need to work for 44 hours. So, 11 " " " " (44x15)/11" = 60 hours