A company employs 15 workers working 44 hours a week to complete a job. If 4 men are ill, how many hours a week would the rest have to works to complete the job?

A 45 hours
B 48 hours
C 50 hours
D 55 hours

Correct Answer: 45 hours

Total work hours per week = 15×44 = 660 hours Workers capable of working = 15 - 4 = 11 Work hour per worker per week needed = 660/11 =  60 hours