If budgeted total direct labour hours are 5500 and budgeted direct labour cost is $755000, then budgeted direct labour cost rate is

If budgeted total direct labour hours are 5500 and budgeted direct labour cost is $755000, then budgeted direct labour cost rate is Correct Answer $137.27 per hour

Budgeted direct labour cost = Budgeted direct labour cost ÷ Budgeted total direct labour hours
= $755000 ÷ 5500 = $137.27 per hour