Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same

Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same Correct Answer A is correct but R is not correct

Related Questions

The addition time in which non-critical activity can consume without increasing the project duration and known as: Where, EFT - Earliest finish Time, LFT - Latest finish Time, LST - Latest start time.