Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same
Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same Correct Answer A is correct but R is not correct