P can do $$\frac{1}{4}$$ th of work in 10 days. Q can do 40% of work in 40 days and R can do $$\frac{1}{3}$$ rd of work in 13 days. Who will complete the work first ?
P can do $$\frac{1}{4}$$ th of work in 10 days. Q can do 40% of work in 40 days and R can do $$\frac{1}{3}$$ rd of work in 13 days. Who will complete the work first ? Correct Answer R
P complete $$\frac{1}{4}$$ th of work in 10 daysSo, P will complete the whole work in 40 days.
Q completes $$\left( {40\% = \frac{2}{5}{\text{th}}} \right)$$ work in 40 days
Q will complete the whole work in = $$\frac{{40 \times 5}}{2}$$ = 100 days
R completes $$\frac{1}{3}$$ work in 13 days
R will complete the whole work in = 39 days
Work will be finished firstly by the man who will take less days to complete it,
So, R will complete it first.