Activity durations in PERT and CPM are decided on the following consideration
Activity durations in PERT and CPM are decided on the following consideration Correct Answer PERT - stochastic, CPM - deterministic
Activity durations in PERT and CPM are decided on the following consideration Correct Answer PERT - stochastic, CPM - deterministic