Mine System Engineering MCQ
Test your knowledge with important Mine System Engineering MCQ and their applications. These MCQs are beneficial for competitive exams too. Explore 30 + more Mine System Engineering MCQs at Bissoy
-
-
A mining machinery company has four plants at locations A, B, C, and D and three warehouses at destinations X, Y and Z. The number of machine units available at the plants A, B, C and D are 5, 8, 7 and 14 respectively. The demands at X, Y and Z are 7, 9 and 18 respectively. The unit costs of transportation in rupees as follows:<br>
-
-
-
-
-
-
-
-
-
A company has three mines at locations A, B and C, which supply coal to power plants at D, E, F and G. Mines A, B and C produce 1800 t/day, 1700 t/day, and 2900 t/day respectively. Daily raw coal requirements at the power plants D, E, F and G from these mines are 2050 t, 1600 t, 1300 t, and 1450 t respectively. Unit transportation costs are as follows:<br>
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-