The key to profitable operation for project cost control, is:
A
To keep the project cost equal to original cost estimate
B
To keep the project cost equal to subsequent construction budget
C
To keep the project cost within the cost budget and knowing when and where job costs are deviating
D
None of these
Correct Answer: To keep the project cost within the cost budget and knowing when and where job costs are deviating