A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by

A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by Correct Answer A manager external to the project

The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.