If the pressure drop for an operation is more than the pressure assigned to the equipment, then the equipment is perfect to be used for that operation.
If the pressure drop for an operation is more than the pressure assigned to the equipment, then the equipment is perfect to be used for that operation. Correct Answer False
In a double pipe heat exchanger we can use the pressure drop less than or equal to the maximum pressure assigned to the equipment, else it may result in high maintenance cost for the equipment and early wear and tear of the HE.