In the case of Shewhart charts, if the data is not according to the normal distribution, the actual in-control ARL (ARL0) will be ____________ the expected value.

In the case of Shewhart charts, if the data is not according to the normal distribution, the actual in-control ARL (ARL0) will be ____________ the expected value. Correct Answer Considerably lower than

It is experimentally determined that if the process data does not follow the normal distribution, then the Shewhart control charts ARL value will be quite less than the value expected based on the normality assumption.