If Cpk=1.0 and Cp=2.0, what will be the actual fallout for the process in ppm?
If Cpk=1.0 and Cp=2.0, what will be the actual fallout for the process in ppm? Correct Answer 1350
If Cpk < Cp, Cpk is considered to evaluate the process fallout as the process is off center and the one sided process capability must be used.