In the cost insitu method the least time required to move formwork is?

In the cost insitu method the least time required to move formwork is? Correct Answer 7

In the cast in situ method at least a week’s time is required to move the formwork to the next incremental length and the precast segment system, the units can be bought to site and lifted by cranes to join them to the previous units by using temporary stressing cables and the rate of construction will be faster in the precast method than in the cast in situ method and in both methods a typical cross section would be a box girder of constant or variable depth.