The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is ___________

The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is ___________ Correct Answer 6.51 m3

Approximately 1.52 m3 of dry concrete is required for 1 m3 of wet concrete. The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is x 1.52 x 15 m3 i.e. 6.51 m3.

Related Questions

How far is point 'R' from Point 'T'? Statement (I): Point 'R' is 5 metres to the north of point 'M'. Point 'U' is 4 metres to the east of point 'R'. Point 'T' is to the west of point 'R' such that points 'U' 'R' and 'T' form a straight line of  metres. Statement (II): Point 'Z' is metres to the south of point 'T'. Point 'U' is  metres to the east of point 'T'. Point 'M' is  metres to the east of point 'Z'. Point 'R' is  metres to the north of point 'M'. Point 'R' lies on the line formed by joining points 'T' and 'U'.