In earthwork calculations, the average horizontal distance between the centre of deposition and the centre of excavation is known as ___________
In earthwork calculations, the average horizontal distance between the centre of deposition and the centre of excavation is known as ___________ Correct Answer Lead
In earthwork calculations, the average horizontal distance between the centre of deposition and the centre of excavation is known as lead. Its unit is 50 m.