In _________________ type of crane, heavy temporary staging or platform is prepared for the working of the crane.

In _________________ type of crane, heavy temporary staging or platform is prepared for the working of the crane. Correct Answer Goliath

In Goliath cranes, heavy loads can be shifted over considerable distances. These cranes are costly and are used in the construction of Harbour works, shops of steel work, etc.

Related Questions

B' was under the regular employment of 'A' as a driver of his mobile crane. He let the crane together with 'B' as driver to 'C'. In the course of loading a ship, 'X' was injured by negligent working of the crane by 'B'. At the time of the accident 'C' had the immediate control and direction of the operations to be executed. The working of the crane and the manipulation of its control, however, remained with 'B', In a suit by 'X' against 'C', is: