Which of the following is incorrect according to the seven objectives of performance measures identified by Ray F. Boedecker?
Which of the following is incorrect according to the seven objectives of performance measures identified by Ray F. Boedecker? Correct Answer Hiding information for making informed decisions
Determination of processes that need improvement, indicating process gains and losses, and comparing goals with actual performance are few of the seven objectives of performance measures identified by Ray F. Boedecker. It also includes providing information to make informed decisions.