The form work is usually removed after ________ for walls, columns, and the vertical faces of all structural components.
The form work is usually removed after ________ for walls, columns, and the vertical faces of all structural components. Correct Answer 24 to 48 hours
In all circumstances, 3/7 of the aforesaid period will suffice for rapid hardening cement, with the exception of vertical sides of slabs, beams, and columns, which should be held for 24 hours.